Construction overhead ans supervision costs?
Posted by admin | Filed under Corporations
mayhm asked:
the basic costs (labor, material and equipment) for various elements of a construction project are:
the basic costs (labor, material and equipment) for various elements of a construction project are:
Excavation – $250,000
Subgrade – $150,000
Base course – $400,000
Concrete pavement – $600,000
Assuming that the field supervision costs is 10% of the basic cost, and the office overhead is 5% of the direct costs (basic costs + field supervision cost), find the prorated field supervision costs, general office overhead costs and the total costs for the various elements of the project.
I dont even know where to begin..an suggestions or help?
thanks in advance
help me please

November 4th, 2009 at 11:17 pm
Calculate pro-rata for all factors to get your question answered.